Project Execution Reports
EPC PipelineTrack stage-by-stage EPC execution, installation progress, engineer workloads and delayed sites.
Total Projects
6
158 kW Total Capacity
Under Installation
1
Rooftop field activity
Portfolio Contract Value
₹95.1 L
Total accepted project value
Delayed / At Risk
1
Requiring supervisor escalation
| Project ID | Customer | Capacity | Stage | Progress | Health | Site Engineer | Value | Due Date |
|---|---|---|---|---|---|---|---|---|
| PRJ-2045 PRJ-2045 | Ahmed Khan | 5 kW | Testing | 75% | Delayed | Imran Sheikh | ₹4.2 L | 2026-09-18 |
| PRJ-2046 PRJ-2046 | Kunal Textiles | 45 kW | Testing | 82% | On Track | Sameer Qureshi | ₹26.1 L | 2026-09-12 |
| PRJ-2047 PRJ-2047 | Om Sai Warehousing | 85 kW | Subsidy | 92% | On Track | Imran Sheikh | ₹46.8 L | 2026-09-20 |
| PRJ-2048 PRJ-2048 | Deshmukh Motors | 10 kW | Installation | 40% | On Track | Sameer Qureshi | ₹7.6 L | 2026-09-25 |
| PRJ-2051 PRJ-2051 | Priya Deshmukh | 3 kW | Documentation | 15% | On Track | Unassigned | ₹2.6 L | 2026-10-05 |
| PRJ-2026-001 PRJ-2026-001 | Rahul Sharma | 10 kW | Handover | 100% | On Track | Imran Sheikh | ₹7.8 L | 2026-08-30 |