Project Execution Reports

EPC Pipeline

Track stage-by-stage EPC execution, installation progress, engineer workloads and delayed sites.

Total Projects

6

158 kW Total Capacity

Under Installation

1

Rooftop field activity

Portfolio Contract Value

₹95.1 L

Total accepted project value

Delayed / At Risk

1

Requiring supervisor escalation

Project IDCustomerCapacityStageProgressHealthSite EngineerValueDue Date
PRJ-2045
PRJ-2045
Ahmed Khan5 kWTesting
75%
DelayedImran Sheikh₹4.2 L2026-09-18
PRJ-2046
PRJ-2046
Kunal Textiles45 kWTesting
82%
On TrackSameer Qureshi₹26.1 L2026-09-12
PRJ-2047
PRJ-2047
Om Sai Warehousing85 kWSubsidy
92%
On TrackImran Sheikh₹46.8 L2026-09-20
PRJ-2048
PRJ-2048
Deshmukh Motors10 kWInstallation
40%
On TrackSameer Qureshi₹7.6 L2026-09-25
PRJ-2051
PRJ-2051
Priya Deshmukh3 kWDocumentation
15%
On TrackUnassigned₹2.6 L2026-10-05
PRJ-2026-001
PRJ-2026-001
Rahul Sharma10 kWHandover
100%
On TrackImran Sheikh₹7.8 L2026-08-30