south_roof_shadow_profile.jpgSite Survey & Rooftop PhotosPRJ-2026-001Imran Sheikh2026-07-03T10:00:00ZAPPROVED
parapet_column_measurements.jpgSite Survey & Rooftop PhotosPRJ-2026-001Imran Sheikh2026-07-03T10:05:00ZAPPROVED
cable_tray_route_feasibility.jpgSite Survey & Rooftop PhotosPRJ-2026-001Imran Sheikh2026-07-03T10:10:00ZAPPROVED
gaikwad_site_feasibility_report.pdfSite Technical Survey & Feasibility ReportPRJ-2026-001Imran Sheikh2026-07-04T14:00:00ZAPPROVED
waaree_540w_delivery_challan.pdfSolar Panels Delivery Challan & Unloading PhotosPRJ-2026-001Imran Sheikh2026-07-15T11:00:00ZAPPROVED
panels_unloading_inspection.jpgSolar Panels Delivery Challan & Unloading PhotosPRJ-2026-001Imran Sheikh2026-07-15T11:15:00ZAPPROVED
module_barcode_scans_19nos.pdfPanel Serial Numbers Sheet & Barcode ScansPRJ-2026-001Imran Sheikh2026-07-16T14:00:00ZAPPROVED
growatt_10kw_serial_number_plate.jpgInverter Delivery Challan & Serial Number PhotoPRJ-2026-001Imran Sheikh2026-07-18T10:30:00ZAPPROVED
polycab_dc_ac_cables_receipt.pdfElectrical BoS Material Delivery ReceiptPRJ-2026-001Imran Sheikh2026-07-19T11:00:00ZAPPROVED
hdg_structure_civil_challan.pdfFabrication Structure & Civil Material Delivery ChallanPRJ-2026-001Imran Sheikh2026-07-20T15:00:00ZAPPROVED
fabrication_dc_signed_copy.pdfStructure Fabrication DC Delivery ChallanPRJ-2026-001Imran Sheikh2026-07-21T16:00:00ZAPPROVED
electrical_dc_challan_verified.pdfElectrical Material DC Delivery ChallanPRJ-2026-001Imran Sheikh2026-07-22T11:30:00ZAPPROVED
structure_torque_inspection.jpgFabrication Structure Inspection PhotosPRJ-2026-001Imran Sheikh2026-07-25T14:00:00ZAPPROVED
structure_tilt_angle_check.jpgFabrication Structure Inspection PhotosPRJ-2026-001Imran Sheikh2026-07-25T14:15:00ZAPPROVED
fabrication_alignment_certificate.pdfFabrication Structure Alignment Inspection ReportPRJ-2026-001Imran Sheikh2026-07-26T16:00:00ZAPPROVED
foundation_ballast_grouting.jpgCivil Foundation Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-27T11:00:00ZAPPROVED
roof_tar_felt_waterproofing.jpgCivil Foundation Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-27T11:20:00ZAPPROVED
acdb_copper_busbar_termination.jpgAC Cabling & Panel Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-29T10:00:00ZAPPROVED
main_lt_panel_solar_breaker.jpgAC Cabling & Panel Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-29T10:20:00ZAPPROVED
dc_string_dressup_under_modules.jpgDC String Cabling & Array Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-30T11:00:00ZAPPROVED
dcdb_fuse_spd_protection.jpgDC String Cabling & Array Work Done PhotosPRJ-2026-001Imran Sheikh2026-07-30T11:25:00ZAPPROVED
chemical_earthing_pit_ac_dc.jpgChemical Earthing Pit Work & Resistance PhotosPRJ-2026-001Imran Sheikh2026-07-31T15:00:00ZAPPROVED
earth_tester_reading_1.2_ohm.jpgChemical Earthing Pit Work & Resistance PhotosPRJ-2026-001Imran Sheikh2026-07-31T15:20:00ZAPPROVED
growatt_wall_mount_glands.jpgInverter Mounting & Termination Work Done PhotosPRJ-2026-001Imran Sheikh2026-08-01T11:00:00ZAPPROVED
inverter_ac_dc_termination_view.jpgInverter Mounting & Termination Work Done PhotosPRJ-2026-001Imran Sheikh2026-08-01T11:25:00ZAPPROVED
dc_combiner_string_check.jpgElectrical Inspection PhotosPRJ-2026-001Imran Sheikh2026-08-02T14:00:00ZAPPROVED
acdb_voltage_measurements.jpgElectrical Inspection PhotosPRJ-2026-001Imran Sheikh2026-08-02T14:15:00ZAPPROVED
insulation_megger_test.jpgElectrical Inspection PhotosPRJ-2026-001Imran Sheikh2026-08-02T14:30:00ZAPPROVED
bos_pre_commissioning_inspection_sheet.pdfElectrical BoS Pre-Commissioning Inspection ReportPRJ-2026-001Imran Sheikh2026-08-03T16:00:00ZAPPROVED
meter_testing_requisition_letter.pdfGeneration Meter Testing Lab Requisition LetterPRJ-2026-001Imran Sheikh2026-08-04T11:00:00ZAPPROVED
msedcl_a1_application_signed.pdfDISCOM Solar Grid Application (A1 Form)PRJ-2026-001Sunita Sharma2026-07-06T10:00:00ZAPPROVED
load_enhancement_form_10kw.pdfLoad Extension ApplicationPRJ-2026-001Sunita Sharma2026-07-07T14:00:00ZAPPROVED
load_enhancement_demand_note_paid.pdfLoad Extension Billing Proof & Fee ReceiptPRJ-2026-001Sunita Sharma2026-07-08T15:30:00ZAPPROVED
msedcl_technical_sanction_order.pdfDISCOM Solar Sanction LetterPRJ-2026-001Sunita Sharma2026-07-10T11:00:00ZAPPROVED
sbi_solar_loan_sanction_pack.pdfSolar Loan Application DocketPRJ-2026-001Sunita Sharma2026-07-11T14:30:00ZAPPROVED
national_portal_app_ack_10kw.pdfPM Surya Ghar Portal Registration AcknowledgementPRJ-2026-001Sunita Sharma2026-07-12T16:00:00ZAPPROVED
pm_surya_ghar_subsidy_sanction.pdfPM Surya Ghar Subsidy In-Principle SanctionPRJ-2026-001Sunita Sharma2026-07-14T10:00:00ZAPPROVED
rts_scheme_portal_clearance.pdfDISCOM RTS Scheme Clearance CertificatePRJ-2026-001Sunita Sharma2026-07-15T14:00:00ZAPPROVED
inverter_green_led_grid_sync.jpgInverter Power-On & Grid Sync PhotoPRJ-2026-001Sunita Sharma2026-08-05T12:00:00ZAPPROVED
discom_joint_inspection_report_jir.pdfDISCOM Joint Project Inspection Report (JIR)PRJ-2026-001Sunita Sharma2026-08-06T15:00:00ZAPPROVED
msedcl_meter_test_certificate_pass.pdfGeneration Meter Lab Test CertificatePRJ-2026-001Sunita Sharma2026-08-07T16:30:00ZAPPROVED
mseb_subdivision_meter_clearance.pdfGeneration Meter Test Clearance Certificate by MSEB/MSEDCLPRJ-2026-001Sunita Sharma2026-08-09T11:00:00ZAPPROVED
net_meter_installed_sealed_box.jpgBi-Directional Net Meter Installation ReportPRJ-2026-001Sunita Sharma2026-08-11T12:00:00ZAPPROVED
old_meter_surrender_final_reading.pdfConsumer Meter Replacement & Removal ReportPRJ-2026-001Sunita Sharma2026-08-12T14:30:00ZAPPROVED
msedcl_official_release_order.pdfDISCOM Net Metering Work Completion & Release LetterPRJ-2026-001Sunita Sharma2026-08-14T11:00:00ZAPPROVED
store_issue_meter_release_note.pdfDISCOM Meter Release Order LetterPRJ-2026-001Sunita Sharma2026-08-15T14:00:00ZAPPROVED
discom_geotagging_endorsement.pdfDISCOM Solar Plant Geo-Tagging CertificatePRJ-2026-001Sunita Sharma2026-08-16T16:00:00ZAPPROVED
meter_rfid_qr_tag_photo.jpgGeneration & Net Meter Tagging Photo/ReportPRJ-2026-001Sunita Sharma2026-08-17T17:00:00ZAPPROVED
portal_field_inspection_signed.pdfPM Surya Ghar Joint Field Inspection ReportPRJ-2026-001Sunita Sharma2026-08-19T11:00:00ZAPPROVED
net_meter_reading_display.jpgSubsidy Meter Reading PhotographPRJ-2026-001Sunita Sharma2026-08-20T14:00:00ZAPPROVED
subsidy_claim_redemption_ack.pdfPM Surya Ghar Subsidy Claim Redemption LetterPRJ-2026-001Sunita Sharma2026-08-22T10:30:00ZAPPROVED
waaree_dcr_manufacturer_certificate.pdfDomestic Content Requirement (DCR) Undertaking & CertificatePRJ-2026-001Sunita Sharma2026-08-23T15:00:00ZAPPROVED
sunpoint_final_tax_invoice_inv1040.pdfEPC Final Tax Invoice (GST Invoice)PRJ-2026-001Sunita Sharma2026-08-24T17:00:00ZAPPROVED
sbi_online_portal_approval.pdfOnline Loan Sanction Letter ApprovalPRJ-2026-001Rahul Bhosale2026-07-13T11:00:00ZAPPROVED
sunil_gaikwad_aadhaar.pdfCustomer Aadhaar CardPRJ-2026-001Priyanka Iyer2026-07-02T10:00:00ZAPPROVED
sunil_gaikwad_pan.pdfCustomer PAN CardPRJ-2026-001Priyanka Iyer2026-07-02T10:15:00ZAPPROVED
electricity_bill_june2026.pdfLatest Electricity BillPRJ-2026-001Priyanka Iyer2026-07-02T10:20:00ZAPPROVED
discom_consumer_ledger.pdfConsumer Light Bill RecordPRJ-2026-001Priyanka Iyer2026-07-02T10:25:00ZAPPROVED
gaikwad_cancelled_cheque.jpgCancelled Bank ChequePRJ-2026-001Priyanka Iyer2026-07-02T10:30:00ZAPPROVED
sbi_bank_passbook_frontpage.jpgBank Passbook CopyPRJ-2026-001Priyanka Iyer2026-07-02T10:35:00ZAPPROVED
signed_work_order_agreement.pdfSigned Purchase Order / Work OrderPRJ-2026-001Priyanka Iyer2026-07-02T11:00:00ZAPPROVED
neft_advance_payment_390000.jpgInitial Advance / First Payment ScreenshotPRJ-2026-001Priyanka Iyer2026-07-02T11:30:00ZAPPROVED
material_delivery_milestone_receipt.jpgMilestone Stage Payment ScreenshotPRJ-2026-001Priyanka Iyer2026-07-23T15:00:00ZAPPROVED
final_10pct_clearance_receipt.jpgFinal Milestone Payment Clearance ScreenshotPRJ-2026-001Priyanka Iyer2026-08-26T14:00:00ZAPPROVED
structure_stability_audit.pdfMounting Structure Stability Inspection ReportPRJ-2026-001Priyanka Iyer2026-07-28T16:00:00ZAPPROVED
dc_side_audit_string_data.pdfDC Side Combiner & Inverter Inspection FilePRJ-2026-001Priyanka Iyer2026-08-03T10:00:00ZAPPROVED
ac_distribution_safety_audit.pdfAC Distribution Board & LT Panel Inspection FilePRJ-2026-001Priyanka Iyer2026-08-03T11:30:00ZAPPROVED
civil_anchoring_audit_photo1.jpgCivil Foundation & Grouting Inspection PhotosPRJ-2026-001Priyanka Iyer2026-07-28T12:00:00ZAPPROVED
civil_anchoring_audit_photo2.jpgCivil Foundation & Grouting Inspection PhotosPRJ-2026-001Priyanka Iyer2026-07-28T12:15:00ZAPPROVED
inverter_display_etoday_42kwh.jpgInverter E-Today & Total Generation Display ScreenshotPRJ-2026-001Priyanka Iyer2026-08-06T17:00:00ZAPPROVED
earth_resistance_calibration_sheet.pdfEarthing Pit Resistance Test & Inspection FilePRJ-2026-001Priyanka Iyer2026-08-02T16:00:00ZAPPROVED
discom_official_metering_inspection_sheet.pdfNet Meter / Generation Meter Official Inspection ReportPRJ-2026-001Priyanka Iyer2026-08-18T14:00:00ZAPPROVED
gaikwad_signed_handover_certificate.pdfCustomer System Handover & Acceptance CertificatePRJ-2026-001Ahmed Sheikh2026-08-25T11:00:00ZAPPROVED
customer_handover_dossier_print_pack.pdfFinal Project Handover Print Dossier Ready SlipPRJ-2026-001Ahmed Sheikh2026-08-25T14:00:00ZAPPROVED
comprehensive_25yr_warranty_pack.pdfSolar Module DCR & Inverter Manufacturer Warranty PackPRJ-2026-001Ahmed Sheikh2026-08-25T16:00:00ZAPPROVED
epc_structural_safety_undertaking.pdfProject Safety Undertaking & Structural Stability DeclarationPRJ-2026-001Ahmed Sheikh2026-08-25T17:00:00ZAPPROVED
as_built_sld_and_roof_cad_drawings.pdfAs-Built Single Line Diagram & Rooftop Layout DrawingsPRJ-2026-001Ahmed Sheikh2026-08-25T18:00:00ZAPPROVED
dc_combiner_wiring.jpgElectrical Inspection PhotosPRJ-2045Imran Sheikh2026-09-02T10:15:00ZPARTIALLY_UPLOADED
acdb_surge_protector.jpgElectrical Inspection PhotosPRJ-2045Imran Sheikh2026-09-02T10:18:00ZPARTIALLY_UPLOADED
ahmed_khan_aadhaar.pdfCustomer Aadhaar CardPRJ-2045Rahul Bhosale2026-08-09T11:00:00ZAPPROVED
electricity_bill_aug2026.pdfLatest Electricity BillPRJ-2045Rahul Bhosale2026-08-09T11:05:00ZAPPROVED
roof_shadow_south.jpgSite Survey & Rooftop PhotosPRJ-2045Imran Sheikh2026-08-12T09:30:00ZAPPROVED
parapet_dimensions.jpgSite Survey & Rooftop PhotosPRJ-2045Imran Sheikh2026-08-12T09:32:00ZAPPROVED
cable_duct_route.jpgSite Survey & Rooftop PhotosPRJ-2045Imran Sheikh2026-08-12T09:35:00ZAPPROVED
panels_delivery_challan_waaree.pdfSolar Panels Delivery Challan & Unloading PhotosPRJ-2045Imran Sheikh2026-08-16T11:00:00ZAPPROVED
barcodes_scan_sheet_ahmed.jpgPanel Serial Numbers Sheet & Barcode ScansPRJ-2045Imran Sheikh2026-08-16T14:30:00ZAPPROVED
growatt_5kw_serial_plate.jpgInverter Delivery Challan & Serial Number PhotoPRJ-2045Imran Sheikh2026-08-18T10:00:00ZAPPROVED
structure_torque_inspection.jpgFabrication Structure Inspection PhotosPRJ-2045Imran Sheikh2026-08-22T11:00:00ZAPPROVED
structure_alignment.jpgFabrication Structure Inspection PhotosPRJ-2045Imran Sheikh2026-08-22T11:30:00ZAPPROVED
grouting_concrete_cubes.jpgCivil Foundation & Grouting Inspection PhotosPRJ-2045Imran Sheikh2026-08-24T14:00:00ZAPPROVED
ballast_surface_sealing.jpgCivil Foundation & Grouting Inspection PhotosPRJ-2045Imran Sheikh2026-08-24T14:20:00ZAPPROVED
earthing_pit_chamber_photos.jpgChemical Earthing Pit Work & Resistance PhotosPRJ-2045Imran Sheikh2026-08-27T10:00:00ZAPPROVED
earth_megger_tester_1.4_ohm.jpgChemical Earthing Pit Work & Resistance PhotosPRJ-2045Imran Sheikh2026-08-27T10:30:00ZAPPROVED
meter_testing_clearance_certificate.pdfGeneration Meter Lab Test CertificatePRJ-2045Sunita Sharma2026-09-03T11:00:00ZSUBMITTED
inverter_sync_led_green.jpgInverter Power-On & Grid Sync PhotoPRJ-2045Imran Sheikh2026-09-03T14:30:00ZSUBMITTED
Bi-Directional Net Meter Installation Report (Pending Upload)MeterPRJ-2045Operations & Documentation Manager—PENDING
DISCOM Net Metering Work Completion & Release Letter (Pending Upload)MeterPRJ-2045Operations & Documentation Manager—PENDING
DISCOM Solar Plant Geo-Tagging Certificate (Pending Upload)MeterPRJ-2026-001Operations & Documentation Manager—PENDING
Customer System Handover & Acceptance Certificate (Pending Upload)HandoverPRJ-2045Project Manager—PENDING
EPC Final Tax Invoice (GST Invoice) (Pending Upload)PaymentPRJ-2045Admin—PENDING
Final Milestone Payment Clearance Screenshot (Pending Upload)PaymentPRJ-2045Admin—PENDING