Field Operations & Daily Tracking

2

Site progress logs, installation milestones, field issues, and daily activity reporting.

PRJ-2045Testing

5 kW System

Installation Progress:75%
PRJ-2046Testing

45 kW System

Installation Progress:82%
PRJ-2047Subsidy

85 kW System

Installation Progress:92%
Work Date:
Showing 2 of 2 records
DateProjectActivity TypeProgress %Site EngineerStatusDescription & IssuesNext Action
2026-09-03PRJ-2045Electrical Installation & DC Cabling75%Imran SheikhIn Progress

Completed string cabling from roof modules to inverter location. Conduit clamped neatly.

Issue: None. Weather was clear.

Complete ACDB connections and prepare for DISCOM meter lab test.
2026-09-02PRJ-2046Testing & Pre-Commissioning82%Sameer QureshiIn Progress

Insulation resistance testing and string open-circuit voltage verification completed.

Joint inspection with MSEDCL sub-engineer.