Field Operations & Daily Tracking
2Site progress logs, installation milestones, field issues, and daily activity reporting.
PRJ-2045Testing
5 kW System
Installation Progress:75%
PRJ-2046Testing
45 kW System
Installation Progress:82%
PRJ-2047Subsidy
85 kW System
Installation Progress:92%
Work Date:
All Sites
All Engineers
All Statuses
Showing 2 of 2 records
| Date | Project | Activity Type | Progress % | Site Engineer | Status | Description & Issues | Next Action |
|---|---|---|---|---|---|---|---|
| 2026-09-03 | PRJ-2045 | Electrical Installation & DC Cabling | 75% | Imran Sheikh | In Progress | Completed string cabling from roof modules to inverter location. Conduit clamped neatly. Issue: None. Weather was clear. | Complete ACDB connections and prepare for DISCOM meter lab test. |
| 2026-09-02 | PRJ-2046 | Testing & Pre-Commissioning | 82% | Sameer Qureshi | In Progress | Insulation resistance testing and string open-circuit voltage verification completed. | Joint inspection with MSEDCL sub-engineer. |