Today's Work & Attendance Report

Role-Wise Audit

Track daily team productivity: document uploads, site visits, sales calls, and multi-site execution audits.

Total Staff Tracked

6

Across 5 operational roles

Worked Today

6(100%)

Active site/office logs

Not Worked Today

0Action Needed

Zero uploads / no updates

Active Sites Covered

5

Distinct EPC rooftops

Document Uploads

95

Photos & inspection files

Completed Service

1

Repairs & AMC closed

PI
Priyanka IyerAdmin

priyanka.iyer@sunpoint.in · +91 98220 01100

WORKED TODAY
AS
Ahmed SheikhProject Manager

ahmed.sheikh@sunpoint.in · +91 98220 01101

WORKED TODAY(3 sites)
SS
Sunita SharmaDocument Manager

sunita.sharma@sunpoint.in · +91 98220 01102

WORKED TODAY(2 sites)
RB
Rahul BhosaleOffice Executive

rahul.bhosale@sunpoint.in · +91 98220 01103

WORKED TODAY(7 sites)

Today's Verified Execution Summary:

Logged 5 follow-up call(s), prepared 3 proposal(s), and uploaded 3 KYC file(s)
Client: Rahul Sharma
  • Completed follow-up: "Share revised quote QT-1052 with 5% discount approval"
Client: Priya Deshmukh
  • Completed follow-up: "Confirm site survey slot for rooftop assessment"
Client: Meera Joshi
  • Completed follow-up: "Send PM Surya Ghar brochure and subsidy slab calculation"
Client: Vikram Patil
  • Completed follow-up: "Initial discovery call regarding monthly electricity consumption"
Client: Ahmed Khan
  • Completed follow-up: "Welcome call and quotation approval confirmation"
PRJ-2026-001· Rahul Sharma (10 kW)
Stage: Handover
  • Uploaded customer verification document: Online Loan Sanction Letter Approval
PRJ-2045· Ahmed Khan (5 kW)
Stage: Testing
  • Uploaded customer verification document: Customer Aadhaar Card
  • Uploaded customer verification document: Latest Electricity Bill
IS
Imran SheikhSite Engineer

imran.sheikh@sunpoint.in · +91 98220 01104

WORKED TODAY(3 sites)

Today's Verified Execution Summary:

uploaded 45 photos, filed 1 site execution log(s), closed 1 after-sales service ticket(s)
PRJ-2026-001· Rahul Sharma (10 kW)
Stage: Handover
  • Uploaded 3 Site Survey & Rooftop Photos file(s)
  • Uploaded 1 Site Technical Survey & Feasibility Report file(s)
  • Uploaded 2 Solar Panels Delivery Challan & Unloading Photos file(s)
  • Uploaded 1 Panel Serial Numbers Sheet & Barcode Scans file(s)
  • Uploaded 1 Inverter Delivery Challan & Serial Number Photo file(s)
  • Uploaded 1 Electrical BoS Material Delivery Receipt file(s)
  • Uploaded 1 Fabrication Structure & Civil Material Delivery Challan file(s)
  • Uploaded 1 Structure Fabrication DC Delivery Challan file(s)
  • Uploaded 1 Electrical Material DC Delivery Challan file(s)
  • Uploaded 2 Fabrication Structure Inspection Photos file(s)
  • Uploaded 1 Fabrication Structure Alignment Inspection Report file(s)
  • Uploaded 2 Civil Foundation Work Done Photos file(s)
  • Uploaded 2 AC Cabling & Panel Work Done Photos file(s)
  • Uploaded 2 DC String Cabling & Array Work Done Photos file(s)
  • Uploaded 2 Chemical Earthing Pit Work & Resistance Photos file(s)
  • Uploaded 2 Inverter Mounting & Termination Work Done Photos file(s)
  • Uploaded 3 Electrical Inspection Photos file(s)
  • Uploaded 1 Electrical BoS Pre-Commissioning Inspection Report file(s)
  • Uploaded 1 Generation Meter Testing Lab Requisition Letter file(s)
PRJ-2045· Ahmed Khan (5 kW)
Stage: Testing
  • Uploaded 2 Electrical Inspection Photos file(s)
  • Uploaded 3 Site Survey & Rooftop Photos file(s)
  • Uploaded 1 Solar Panels Delivery Challan & Unloading Photos file(s)
  • Uploaded 1 Panel Serial Numbers Sheet & Barcode Scans file(s)
  • Uploaded 1 Inverter Delivery Challan & Serial Number Photo file(s)
  • Uploaded 2 Fabrication Structure Inspection Photos file(s)
  • Uploaded 2 Civil Foundation & Grouting Inspection Photos file(s)
  • Uploaded 2 Chemical Earthing Pit Work & Resistance Photos file(s)
  • Uploaded 1 Inverter Power-On & Grid Sync Photo file(s)
  • Electrical Installation & DC Cabling: Completed string cabling from roof modules to inverter location. Conduit clamped neatly. (75% completed, In Progress)
  • [After-Sales Service Closed] Ticket TCK-203 (MCB / Tripping / Earth Fault): Replaced blown 1000V DC surge fuse, inspected earthing pit resistance (measured 2.4 ohms, safe). System tested and generating 4.2 kW normally. (Customer Sign-Off: Vikram Malhotra)
RD
Rajesh DeshmukhClient

customer@sunpoint.in · +91 98220 12345

WORKED TODAY