EPC PROJECT
PRJ-2047
On TrackOm Sai Warehousing · 85 kW System · Talegaon, Maharashtra
Contract Value (Incl. Tax)
₹46.8 L
Due Date: 20 Sept 2026
Current Stage: Subsidy92% Complete
Project ManagerAhmed Sheikh
Assigned Site EngineerImran Sheikh
Documentation Compliance0 / 57 (0%)
Payments Collected₹0
Milestone Status & Execution Timeline
Quotation Accepted:QT-1056
Current Execution Milestone:Subsidy
Contract Due Date:2026-09-20
Health Assessment:On Track
Financial & Cost Snapshot
Total Contract Value:₹46.8 L
Actual Net Material Cost:₹0
Approved Project Expenses:₹0
Total Actual Cost:₹0
Gross Project Profit:₹46.8 L (100%)