Project IDCustomerCapacityContract ValueProject ManagerSite EngineerStageProgressDue DateHealth
PRJ-2045Ahmed Khan
CUST-001Pune
5 kW₹4.2 LAhmed SheikhImran SheikhTesting
75%
18 SeptDelayed
PRJ-2046Kunal Textiles
CUST-005Bhosari
45 kW₹26.1 LAhmed SheikhSameer QureshiTesting
82%
12 SeptOn Track
PRJ-2047Om Sai Warehousing
CUST-010Talegaon
85 kW₹46.8 LAhmed SheikhImran SheikhSubsidy
92%
20 SeptOn Track
PRJ-2048Deshmukh Motors
CUST-007Hadapsar
10 kW₹7.6 LAhmed SheikhSameer QureshiInstallation
40%
25 SeptOn Track
PRJ-2051Priya Deshmukh
CUST-004Pune
3 kW₹2.6 LAhmed SheikhUnassignedDocumentation
15%
05 OctOn Track
PRJ-2026-001Rahul Sharma
CUST-002Pune
10 kW₹7.8 LAhmed SheikhImran SheikhHandover
100%
30 AugOn Track