Admin
EPC PROJECT

PRJ-2048

On Track

Deshmukh Motors · 10 kW System · Hadapsar, Maharashtra

Contract Value (Incl. Tax)

₹7.6 L

Due Date: 25 Sept 2026

Current Stage: Installation40% Complete
Project ManagerAhmed Sheikh
Assigned Site EngineerSameer Qureshi
Documentation Compliance0 / 57 (0%)
Payments Collected₹0

Milestone Status & Execution Timeline

Quotation Accepted:QT-1055
Current Execution Milestone:Installation
Contract Due Date:2026-09-25
Health Assessment:On Track

Financial & Cost Snapshot

Total Contract Value:₹7.6 L
Actual Net Material Cost:₹0
Approved Project Expenses:₹0
Total Actual Cost:₹0
Gross Project Profit:₹7.6 L (100%)